I would like to know what is the best practice for Actual , Budgeting and forecasting.

Option 1: Create a separate Version Dimension

Option 2: Create Scenario for Actual, Budgeting and forecasting

icon

Best answer by WILLIAM.MONTERO 15 April 2023, 01:26

View original

2 replies

Userlevel 1
Badge

Hey @abhilashsawla ,

I’d say the best practice is Option 2. I’m expecting the supporting functions for Scenarios to keep improving so the best long-term experience will be with that choice.

I think you were also in the thread when Nathan helped with a similar question.

Best practices for budget/forecast

Userlevel 4
Badge +5

Thanks @WILLIAM.MONTERO 